For steel frames & truss works

How to apply Rust Shield®

Block moisture. Stop rust. Protect steel.

For steel door frames, window frames, truss works and fabricated steel. The rust has to come off before the coating goes on — everything after that is two even coats and a cure.

  • 6 steps
  • 2 coats
  • Direct apply
  • Recoat 2–3 hrs
  • Hard dry 5–8 hrs

Applying Rust Shield, step by step

  1. A gloved hand scouring rust off a mild-steel frame with a wire brush, bright bare metal appearing

    01 Step 1 of 6

    Remove rust and clean the steel

    Take the corrosion back to sound metal. A wire brush, sandpaper or any suitable cleaning method will do it.

    • Remove all existing rust with a wire brush, sandpaper or emery.

    • Take off loose mill scale, flaking paint and weld spatter as well.

    • Degrease: the surface must be free from oil, grease, dust and loose particles.

    • The steel must be dry. Never coat a wet surface.

    Back to sound, bright metal

  2. An open 1 litre PRIME GUARD LACCO+ Rust Shield tin on a workbench, a stirring stick lifting a ribbon of the thick black coating out of it

    02 Step 2 of 6

    Stir well before use

    The protective solids settle while the tin stands. Stir from the bottom until the colour and the body are even the whole way through.

    • Stir thoroughly, lifting from the bottom of the tin, every time you start.

    • Do not thin it. RUST SHIELD is direct apply — no primer needed.

    • Close the container tightly after use.

    • Work in a well-ventilated area, in goggles, mask and gloves.

    Direct apply — no primer, no thinner

  3. A gloved hand brushing black Rust Shield into the welded corner joint of a steel door frame

    03 Step 3 of 6

    Apply using brush or roller

    An even coat straight onto the cleaned metal. The joints and the buried faces matter more than the face you can see.

    • Lay an even coat with a brush or roller — no primer first.

    • Cover the contact area between the wall and the metal frame.

    • Work the coating into welds, corners, cut ends and fixing holes.

    • Do not apply on wet surfaces or during rain.

    First coat

  4. A freshly coated black steel door frame standing alone on a workshop floor while the first coat dries

    04 Step 4 of 6

    Allow to dry 2–3 hours

    Let the first coat dry before the second goes on. Two to three hours is the recoat window; humid weather takes the long end of it.

    • Stand the frame where air reaches every face while it dries.

    • Keep it out of rain, spray and settling dust.

    • Touch-test a hidden edge: dry, not tacky, before you recoat.

    • Do not force-dry with heat.

    2–3 hrs before the second coat

  5. A gloved hand brushing a glossier second coat over the dried first coat on a steel window frame

    05 Step 5 of 6

    Apply the second coat

    The second coat is what closes the barrier over the metal. Same method, same attention to the joints.

    • Same even coat, over every face the first coat reached.

    • Check welds, corners and the wall-contact area again for thin spots.

    • Do not stop at one coat — the film needs both to seal properly.

    • Close the tin tightly as soon as you are finished.

    Second coat

  6. A finished satin-black coated steel door frame with water beading off the metal and no trace of rust

    06 Step 6 of 6

    Cure, then install

    Allow 5–8 hours for a hard dry. Install or finish the frame only once the coating has properly cured.

    • 5–8 hours for a hard dry before handling, fixing or finishing.

    • Water should run straight off the coated metal instead of clinging to it.

    • Touch up any scratch from handling before the frame is built in.

    • Store the remaining tin closed, cool, dry and out of direct sunlight.

    Hard dry 5–8 hrs

Reference

Timings & safety

Timings

Coats
2
Recoat after
2–3 hrs
Hard dry
5–8 hrs
Primer
None
Net content
1 Litre

Safety

  • Avoid contact with eyes and skin.
  • Wear goggles, a dust mask and gloves.
  • Do not breathe in vapour or spray.
  • Use in a well-ventilated area.
  • Keep out of reach of children.

Storage

  • Close the container tightly after use.
  • Store cool and dry, out of direct sunlight.
  • 24 months unopened, from the date of manufacture.
  • Coverage varies with surface condition, roughness and film thickness.

Unsure about a junction on your site?

Send us a photo and the substrate and we will tell you which product to use and how much you need.